12399456https://www.upal.com.my/zh/feeds/jobFeedKwongwahArray ( [0] => HTTP/1.1 500 Internal Server Error [1] => Date: Sat, 30 Nov 2024 07:32:05 GMT [2] => Content-Type: text/html; charset=UTF-8 [3] => Connection: close [4] => X-Powered-By: PHP/7.4.33 [5] => Cache-Control: no-cache, private [6] => X-Frame-Options: SAMEORIGIN [7] => X-XSS-Protection: 1; mode=block [8] => X-Content-Type-Options: nosniff [9] => Referrer-Policy: no-referrer-when-downgrade [10] => CF-Cache-Status: DYNAMIC [11] => Report-To: {"endpoints":[{"url":"https:\/\/a.nel.cloudflare.com\/report\/v4?s=yPy6w6%2F66m3MSKLzVX5dwpGlKz06EecuE8WP4m%2BXtoRFCM%2BpU1rxReiqjRbBCxeYNMO1mZHFTcI%2BS9iGhhegA2B90tLHKhH2RcBi8DVo0YJgcnUom%2BiKmoEz0MoOFNc6etg%3D"}],"group":"cf-nel","max_age":604800} [12] => NEL: {"success_fraction":0,"report_to":"cf-nel","max_age":604800} [13] => Server: cloudflare [14] => CF-RAY: 8ea9243e7ea52aa1-LAX [15] => alt-svc: h3=":443"; ma=86400 [16] => server-timing: cfL4;desc="?proto=TCP&rtt=194829&min_rtt=194726&rtt_var=54829&sent=5&recv=6&lost=0&retrans=0&sent_bytes=2999&recv_bytes=756&delivery_rate=14872&cwnd=33&unsent_bytes=0&cid=bb60f165a587cc3c&ts=841&x=0" ) 789

 

东海岸铁路计划

 

首相敦马哈迪医生指出,中国交通建设股份有限公司(CCCC)已同意退还原本东海岸铁路计划合约第2阶段工程所收取31亿令吉的部分预付款项予我国。

他说,中国交建将在今年4月12日起一周内退还5亿令吉,另外5亿令吉将在该日期的一个月内退还,总额10亿令吉。

他说,另外扣除东铁工程暂停及展延,以及北部路线取消的核实索偿后,余额将在3月内退还。

- Advertisement -

他今日在新闻发布会上,这么说。中国交建与大马铁路衔接私人有限公司在4月12日签署附加协议。

在附加协议,东铁第一及第二阶段工程成本将降至440亿令吉,比原本的655亿令吉削减了215亿令吉。

马哈迪指出,修改后的东铁成本从原本每公里9550万令吉降至6870万令吉。

新路线将涵盖20个站,从哥打巴鲁至瓜拉登嘉楼、关丹、文德甲,再衔接至日叻务、万宜/加影、布城中环及巴生港口。

- Advertisement -

路线调整后将经过5个州属及布城,之前只有4州,让更多州属受惠。

新南部路线将直接衔接关丹港口至巴生港口,作为两个港口的桥梁。

马哈迪说,新路线也将利用吉隆坡国际机场快铁及第二捷运路线,在布城中环站设转换站。